Méthode d'analyse des coûts du cycle de vie

The life-cycle cost analysis method is the most commonly accepted method to assess the economic benefits of energy conservation projects over their lifetime. Typically, the method is used to evaluate at least two alternatives of a given project (for instance, evaluate two alternatives for the installation of a new HVAC system: a VAV system or a heat pump system to condition the building). Only one alternative will be selected for implementation based on the economic analysis.

Coût du cycle de vie dans la construction

The basic procedure of the LCC method is relatively simple because it seeks to determine the relative cost-effectiveness of the various alternatives. For each alternative including the base case, the total cost is computed over the project lifetime. The cost is commonly determined using one of two approaches: the present worth or the annualized cost estimate. Then, the alternative with the lowest total cost (or LCC) is typically selected.

Diagramme de flux de trésorerie

Using the cash flow diagram of Figure above, the LCC amount for each alternative can be computed by projecting all the costs (including costs of acquisition, installation, maintenance, and operating the energy systems related to the energy-conservation project) on either:

  • Un seul montant en valeur actuelle qui peut être calculé comme suit :

Il s’agit de l’approche la plus couramment utilisée pour calculer le CCV dans les projets de rénovation énergétique.

  • Coûts annualisés multiples sur la durée de vie du projet :
Coût annualisé multiple

Notez que les deux approches de calcul des valeurs LCC sont équivalentes.
Dans la plupart des projets d’efficacité énergétique, le flux de trésorerie annuel reste le même après l’investissement initial.
Dans ce cas, le LCC peut être estimé sur la base du coût initial IC et du coût annuel AC comme suit :

formule du coût du cycle de vie
Table des matières

Exemple

A building owner has $10,000 available and has has three options to invest his money as briefly described below:

  • Replace the entire older boiler (including burner) with more efficient heating system. The old boiler/burner system has an efficiency of only 60 percent whereas a new boiler/burner system has an efficiency of 85 percent. The cost of this replacement is $10,000.
  • Replace only the burner of the old boiler. This action can increase the efficiency of the boiler/burner system to 66 percent. The cost of the burner replacement is $2,000.
  • Ne faites rien et ne remplacez ni la chaudière ni le brûleur.

Determine the best economical option for the building owner. Assume that the lifetime of the retrofit project is ten years and the discount rate is 5 percent. The boiler consumes 5,000 gallons per year at a cost of $1.20 per gallon. An annual maintenance fee of $150 is required for the boiler (independently of its age). Use the life-cycle cost analysis method to determine the best option.

La solution

The total cost of operating the boiler/burner system is considered for the three options. In this analysis, the salvage value of the boiler or burner is neglected. Therefore, the only annual cash flows (A) after the initial investment on a new boiler are the maintenance fee and the net savings due to higher boiler efficiency. To present the calculations for LCC analysis, it is recommended to present the results in a tabular format and proceed as shown below:

Par conséquent, le coût du cycle de vie de l’option A est le plus bas. Ainsi, il est recommandé au propriétaire du bâtiment de remplacer l’ensemble du système chaudière/brûleur.

This conclusion is different from that obtained by using the simple payback analysis [indeed, the payback period for option A, relative to the base case C, is SPB(A) = ($10,000)/($1,765) = 5.66 years; and for option B, SPB(B) = ($2,000)/ ($546) = 3.66 years].

Note that if the discount rate were d = 10 percent (which is unusually high for most markets), the USPW would be equal to USPW = 6.145 and the life-cycle cost for each option will be

Par conséquent, l’option B deviendra la plus efficace sur le plan économique et sera l’option recommandée au propriétaire du bâtiment.

[dvfaqtopic title=”FREQUENTLY ASKED QUESTIONS” topicid=”18932″ skin=”custom” searchbox=”no” switcher=”yes” paginate=”” order=”ASC” orderby=”date”]